Governance, RACI, milestones, risks, deliverables and investment for the 20-week Company A × Company B integration.

Programme week
14 / 20
Target go-live: Jul 2026
Phase
3 · Integrate
Weeks 13–16 · prod rollout
RAG status
Green · on track
7 of 11 milestones complete
Workstreams
4 active · 0 blocked
Programme phases · 20 weeks
Phase 1 — Discover
completed
Weeks 1–4
100%

Architecture design, API catalogue, data mapping, IAM audit, infrastructure discovery

ADRs · API Inventory · IAM Design Doc
Phase 2 — Build
in progress
Weeks 5–12
78%

API gateway build, schema registry, SSO staging, CI/CD unification, K8s migration begins

API Gateway (non-prod) · Canonical Schema v1 · SSO Staging
Phase 3 — Integrate
in progress
Weeks 13–16
32%

Production API rollout, data pipeline live, K8s consolidation, monitoring unified

Unified API (prod) · Canonical Data Pipeline · Merged CI/CD
Phase 4 — Validate
pending
Weeks 17–20
8%

UAT across all workstreams, security assessment, performance testing, go-live

UAT Sign-off · Security Report · Production Go-Live
Milestones · critical path
PhaseMilestoneDeliverableTargetStatus
P1Integration architecture sign-offArchitecture Decision Record Week 3
completed
P1API catalogue completeAPI Inventory Document Week 4
completed
P2API gateway live (non-prod)Gateway Config + Docs Week 7
completed
P2Event schema v1 ratifiedSchema Registry Entry Week 8
completed
P2IAM design approvedIAM Design Document Week 6
completed
P3SSO integrated (staging)SSO Test Report Week 10
in progress
P3Unified CI/CD pipeline livePipeline Runbook Week 12
in progress
P3Data model v1 in prodData Model Docs Week 14
in progress
P4Full UAT passedUAT Sign-off Report Week 17
pending
P4Pen test clearedSecurity Assessment Report Week 18
pending
P4Production go-liveGo-Live Checklist Week 20
pending
Governance cadence
Engineering footprint
Paris
Company A HQ · Platform
92
Amsterdam
Company A · Carrier integrations
38
Munich
Company A · Enterprise
22
Madrid
Company A · Data
18
Hamburg
Company B HQ · Workflow
41
Bangalore
Company B · Engineering hub
89
300 engineers across 6 hubs · async-first collaboration model