Workspace, team, security, notifications and integrations for the integration programme.

Plan

Enterprise programme contract — co-funded by Company A & Company B.

Enterprise Programme
$258,500 / 20-week engagement
Includes 225 person-days · 24×7 support · SOC 2 audit support
Spent to date
$182,210
70% of budget
Forecast at completion
$251,400
2.8% under
Open commitments
$36,800
6 POs